VA Lenders Handbook (VA Pamphlet 26-7), Chapter 9, Topic 10 — Escrow for Postponed Completion of Improvements
VA Lenders Handbook (VA Pamphlet 26-7), Chapter 9, Topic 10 — Escrow for Postponed Completion of Improvements.
Verbatim regulatory text
Verbatim provisions from VA Lenders Handbook (VA Pamphlet 26-7), Chapter 9, Topic 10 — Escrow for Postponed Completion of Improvements — each quote is a verified substring of the regulator-published source snapshot, not retyped. Quoted for reference; this is not legal advice. The operational layer (P&P updates, prompts) lives in the regulation update kits.
VA Pamphlet 26-7, Chapter 9 (Legal Instruments, Liens, Escrows, and), Topic 10 — Escrow for Postponed Completion of Improvements
Topic 10. Escrow for Proposed Completion of Improvements Change Date: July 30, 2019 This chapter has been revised in its entirety. a. Policy In some instances, it may not be possible to complete certain items before the Veteran wishes to move into the property. The escrow of funds can permit the Veteran-purchaser to gain occupancy of the dwelling prior to completion of certain items which must be postponed due to weather conditions or other circumstances. Such items include, but are not limited to: walkways, driveways, and retaining walls, exterior painting, landscaping, and garages. b. Escrow of Funds to Complete Unfinished Work VA may permit the escrow of funds necessary to complete the unfinished work later, and still issue evidence of guaranty. An escrow involves the following: withholding 1 1/2 times the dollar amount necessary to complete the postponed items (as estimated by a third party) from the proceeds due the seller at closing, holding the escrowing funds in a proper, secure manner, and releasing the funds once the postponed items have been satisfactorily completed. c. Establishing an Escrow Fund To establish an escrow, the following must apply: construction of the dwelling must be complete and the house must be suitable for immediate occupancy, postponement of the improvements must be beyond the control of the builder/seller, the duration of the postponement must not be unreasonable (usually 90 to 120 days), and the amount escrowed must be at least 1 1/2 times an estimate of the amount needed to complete the work. Lenders are not required to escrow funds when: the incomplete work is limited to the installation of landscaping features due to inclement weather (lawns, shrubbery, etc.), the estimate of the cost to complete the work is not greater than $2,500, and there is adequate assurance that the work will be completed timely and satisfactorily (usually 90 to 120 days). d. General Procedures No prior approval of VA is required to escrow funds. Lenders are responsible for establishing escrows in accordance with the guidelines presented in this topic. Lenders are also responsible for assuring that the postponed work is completed. Once the loan closes, VA will randomly monitor cases to ensure completion of escrowed items. Table 4: Procedures for Escrows for Postponed Completion of Improvements Step Action 1 Close loan and escrow the required funds. 2 Upload the closed loan package into WebLGY for issuance of guaranty with: lender evidence of an escrow agreement, or a completed VA Form 26-1849, Escrow Agreement for Postponed Exterior Onsite Improvements. 3 Release escrowed funds when work is satisfactorily completed, as evidenced by doing the following: Complete VA Form 26-1839, Compliance Inspection Report, indicating the postponed work has been satisfactorily completed, or if the postponed work is minor, uncomplicated, and not involving structural issues, provide written certification from the lender indicating the work has been completed, and a statement from the Veteran- purchaser that he or she is satisfied with the work. e. Letter of Credit A commercial letter of credit may be used in lieu of a cash escrow provided: the dollar amount of available credit is at least 1 1/2 times the estimated cost of the postponed work, a trust agreement describing the duties, obligations, and responsibilities is submitted (VA Form 26-1849 may be used), the letter of credit is irrevocable and a valid and binding obligation on the issuing bank and extends at least 6 months beyond the date for completion of improvements, and a copy of the letter of credit and trust agreement is furnished to the appropriate VA office so a control can be maintained on the available credit.
Get this regulation in your AI window
Retired VA chapter text stays online for years. An assistant will blend a superseded topic with a live one and cite neither.Put the verbatim text and its effective date in front of your assistant, instead of whatever it remembers.
Open in Claude Open in ChatGPT
Open in Claude shows the one-time setup: paste one address, no account with us. Open in ChatGPT asks ChatGPT about this page, with no setup. Either way it’s free.
Next step: the VA loan QC playbook. Run it in your AI window →
Get notified if this rule changes
One email when VA Lenders Handbook (VA Pamphlet 26-7), Chapter 9, Topic 10 — Escrow for Postponed Completion of Improvements changes: what changed, the new verbatim text, and the effective date. Nothing else.
Double opt-in: we send a confirmation link first. Following one section does not subscribe you to anything else. Privacy.
Source of record: https://claudeforcompliance.com/regs/va-m26-7-ch09-t10/
· register va-m26-7-ch09-t10 · verbatim, source-snapshotted regulator text from the
Claude for Compliance corpus. To work from every register at once, download the corpus
and follow the methodology.