Verbatim provisions from VA Lenders Handbook (VA Pamphlet 26-7), Chapter 10, Topic 15 — Warranty Requirements for New Construction — each quote is a verified substring of the regulator-published source snapshot, not retyped. Quoted for reference; this is not legal advice. The operational layer (P&P updates, prompts) lives in the regulation update kits.
VA Pamphlet 26-7, Chapter 10 (Appraisal Process), Topic 15 — Warranty Requirements for New Construction
Topic 15. Warranty Requirements for New Construction Change Date: March 11, 2019 This Chapter has been revised in its entirety. a. New Construction Warranties On a new construction property, the Veteran must be provided with: a 1-year warranty on VA Form 26-1859, Warranty of Completion of Construction, or a 10-year, insurance backed warranty. b. Evidence of Construction Completion Evidence that the new construction property was satisfactorily completed will be documented as follows: If the local authority performs foundation, framing and final inspections, VA will accept the certificate of occupancy as evidence of local authority inspections and satisfactory completion of construction in compliance with local building code requirements. If the local authority does not issue a certificate of occupancy, copies of the three satisfactory inspection reports or a written statement from the local authority confirming the three inspections were completed and that the construction was found to be satisfactory will be acceptable. If the local authority does not provide construction inspections, the lender must certify that the property is complete (both on-site and off-site improvements), and that it meets VA MPRs for existing construction (see Chapter 12 of this Handbook).
Get this regulation in your AI window
Retired VA chapter text stays online for years. An assistant will blend a superseded topic with a live one and cite neither.Put the verbatim text and its effective date in front of your assistant, instead of whatever it remembers.
Open in Claude Open in ChatGPT
Open in Claude shows the one-time setup: paste one address, no account with us. Open in ChatGPT asks ChatGPT about this page, with no setup. Either way it’s free.
The VA loan QC playbook uses this rule. Run it in your AI window →
Get notified if this rule changes
One email when VA Lenders Handbook (VA Pamphlet 26-7), Chapter 10, Topic 15 — Warranty Requirements for New Construction changes: what changed, the new verbatim text, and the effective date. Nothing else.
Double opt-in: we send a confirmation link first. Following one section does not subscribe you to anything else. Privacy.
Source of record: https://claudeforcompliance.com/regs/va-m26-7-ch10-t15/
· register va-m26-7-ch10-t15 · verbatim, source-snapshotted regulator text from the
Claude for Compliance corpus. To work from every register at once, download the corpus
and follow the methodology.